A pre-engineered building is designed, detailed, fabricated and erected as one system, and drawings are how the information moves between those stages. The client needs to check what they are buying, the civil contractor needs to build the foundations, the shop needs to cut and weld plates, and the erection team needs to know where every piece goes.
This post walks through a typical PEB drawing set in the order it is usually issued, and what each audience should look for.
The drawing set at a glance
| Drawing | Main user | Answers the question |
|---|---|---|
| Anchor bolt plan | Civil contractor, foundation designer | Where are the bolts and what loads go into the foundation? |
| General arrangement (GA) | Client, consultant, architect | What exactly is being built? |
| Frame cross-sections | Engineer, client, erection team | What does each frame look like? |
| Roof framing plan | Erection team, client | Where are the purlins, bracing and openings in the roof? |
| Wall framing elevations | Erection team, client | Where are the girts, doors, windows and wall bracing? |
| Bracing details | Engineer, erection team | How is the building kept stable? |
| Sheeting and trim layout | Sheeting crew, client | Which sheets, flashings and gutters go where? |
| Erection drawings | Erection team | Which piece goes where and how is it bolted? |
| Shop drawings | Fabrication shop | How is each piece made? |
Anchor bolt plan
The anchor bolt plan is usually the first drawing issued, because foundations are cast while the steel is still in the shop. It shows:
- Grid lines and overall dimensions.
- Column positions and orientation.
- Anchor bolt diameter, number, spacing, projection above concrete and embedment.
- Base plate size and grout thickness.
- Support reactions for the foundation designer, by load case or combination.
What the client and site team should check: that the grid matches the architectural layout, that the bolt projections and levels are clear, and that the reactions are given in a form the foundation designer can use. A mistake here is costly because it is cast in concrete.
General arrangement (GA) drawings
The GA drawings describe the whole building: plan, roof plan, side and end elevations and a typical section. They show overall dimensions, eave height, roof slope, frame spacing, openings, canopies, mezzanines and crane positions, and they usually carry the design basis notes: codes, loads and materials.
What the client should check: dimensions, clear heights, door and window positions, canopy sizes and the design loads. The GA is the drawing to approve before fabrication starts. If something is wrong on the GA, it will be wrong in the building.
Frame cross-sections
Each distinct frame type gets a cross-section drawing showing the column and rafter profile, the tapered depths, the flange and web plate sizes for each segment, the splice and knee positions, the flange brace locations and the base condition.
What to look for: the frame types match the GA (end frames, interior frames, crane frames, mezzanine frames), and the connection positions are practical for transport and erection. Engineers also use these sheets to cross-check the design output.
Roof framing plan
The roof framing plan shows purlin positions and sizes, lap lengths, sag rods, roof bracing, eave struts and openings for skylights, ventilators or roof monitors.
What the erection team needs: the purlin spacing, lap positions and which bays carry bracing. Missing sag rods or bracing in the wrong bay are common site errors that this drawing should prevent.
Wall framing elevations
One elevation per wall shows girt positions and sizes, wind columns at end walls, door and window framing, wall bracing and any brick wall height below the cladding.
What the client should check: door and window positions and sizes, and whether the brick wall height matches the civil drawings.
Bracing details
Bracing keeps a PEB stable along its length and against wind on the end walls. The bracing drawings show roof bracing, wall bracing (rod, angle or portal frame bracing where doors block diagonal bracing) and their connections.
What the erection team needs: which bays are braced, the tensioning requirement for rod bracing and the sequence. Bracing should be installed as erection proceeds, not left for the end.
Sheeting and trim layout
These drawings show roof and wall sheet profiles, lengths and laps, flashings, ridge, gutters, downtakes, skylights and insulation.
What the sheeting crew and client need: sheet lengths and laps, flashing positions and the gutter and downtake layout. Most leaks come from flashing and lap details, not from the sheets themselves.
Erection drawings
Erection drawings combine the plans and elevations with piece marks for every member, and connection details showing bolt sizes, grades and numbers. Many suppliers also include an erection sequence and notes on temporary bracing.
What the erection team needs: a clear piece mark on every member, bolt details for every joint, and whether bolts are pretensioned. These drawings should match the marks painted on the steel. See PEB connection design basics for why bolt grade and pretension matter.
Shop drawings
Shop drawings, also called fabrication drawings, show each piece individually: plate sizes, cutting dimensions, hole positions, weld sizes, stiffeners, end plates, surface preparation and painting. Cold-formed members have their own cutting and punching lists.
Who uses them: the fabrication shop and quality inspectors. Clients rarely review shop drawings, but they can ask for the material list to check against the take-off. Our guide on PEB tonnage estimation and steel take-off explains how the quantities relate to the drawings.
Making the set consistent
The biggest problem with PEB drawings is not missing sheets; it is sheets that disagree with each other. A door moved on the GA but not on the wall elevation, or a frame changed in the design but not on the anchor bolt plan, causes problems on site. A few practices help:
- Generate drawings from the same model that was designed, so dimensions and sections come from one source.
- Keep a revision log on every sheet, and reissue all affected sheets together.
- Use a consistent house style for layers, text and dimensions, so anyone in the office can read any job.
- Freeze the anchor bolt plan before the foundations are cast.
Design software can help with the first and third points. Ganithva, for example, produces DXF elevation and plan drawings from the designed model in the office’s own house style, and the engineer reviews them before issue. See how our PEB design software works.
Whatever the tools, every drawing that leaves the office should be checked and approved by the responsible engineer.
Frequently asked questions
Which PEB drawing is needed first?
The anchor bolt plan. The civil contractor needs it to cast the foundations and set the anchor bolts, and that work usually starts while the steel is still being fabricated. It should be issued early and frozen, because changes after the concrete is cast are expensive.
What is the difference between erection drawings and shop drawings?
Erection drawings show where each piece goes in the building and how it connects, using piece marks. Shop drawings show how each individual piece is made: plate sizes, cuts, holes and welds. Site teams use erection drawings; the fabrication shop uses shop drawings.
Should the client approve PEB drawings?
Usually the client or their consultant approves the GA drawings and the anchor bolt plan before fabrication starts. This confirms the dimensions, openings, loads and foundation reactions. Shop drawings are normally checked internally by the supplier.
What should be on a PEB anchor bolt plan?
Grid lines and dimensions, column positions, anchor bolt sizes, numbers and projections, base plate details, the finished floor and grout levels, and the support reactions for each load case or combination that the foundation designer needs.