# How to quote a PEB faster: from enquiry to quotation

Most PEB orders go to the supplier who sends a clear, believable quotation first. Speed comes from a fixed workflow, not from guessing the tonnage.

16 NOVEMBER 2026 · 7 MIN READ

**Key points**

- A PEB quotation is faster with a fixed workflow: a complete enquiry checklist, a written design basis, a preliminary design, a tonnage and BOQ take-off, a clear price structure and a short review.
- The written design basis decides PEB tonnage more than any other choice: the member design code, load codes, basic wind speed and terrain, roof collateral and live loads, and deflection limits.
- A rate per square metre is only a sanity check for a PEB quotation, because span, height, wind zone and crane loads can change the steel weight substantially for the same floor area.
- A clean PEB quotation BOQ separates primary steel, secondary steel, bracing, sheeting and accessories, bolts and fasteners, and extras such as canopies, staircases and doors.
- Two PEB quotations for the same building usually differ because the design basis differs, so they should be compared on the same wind speed, deflection limits and collateral load before comparing prices.

At a pre-engineered building company, the estimation desk sits between sales and design. An enquiry arrives by email or phone, often with a rough sketch and a deadline, and the client is asking several suppliers at the same time. The supplier who replies first with a clear, defensible number has an advantage. The supplier who replies first with a wrong number has a problem.

This post walks through a practical enquiry-to-quotation workflow used in Indian PEB practice, and the mistakes that slow it down or make it expensive later.

## Step 1: Ask the right questions in the enquiry

Most delays in quoting come from missing information. A good enquiry checklist, sent back to the client on the same day, saves several rounds of calls. The core items are:

| Group | What to ask |

| Geometry | Length, width, clear height or eave height, roof slope, number of spans, frame spacing if fixed |

| Location | Site address or district, for basic wind speed, seismic zone and terrain |

| Use | Warehouse, factory, cold store, workshop; any special fire or hygiene needs |

| Cranes | Capacity, span, number, duty class, hook height, rail level |

| Mezzanines | Area, use, live load, finish (deck slab or grating) |

| Roof and wall | Sheeting type and thickness, insulation, skylights, ventilators, wall cladding height, brick wall below |

| Openings | Doors, rolling shutters, louvres, canopies and their sizes |

| Extra loads | Solar panels, hung services, sprinklers, false ceiling |

| Scope | Supply only, supply and erection, foundation and civil scope, anchor bolts |

| Commercial | Required delivery date, GST and freight basis, payment terms expected |

If the client does not know an answer, write down the assumption you are making. That assumption becomes part of the offer.

## Step 2: Fix the design basis

Before any design starts, write the design basis in a few lines: the code for member design (IS 800:2007, or AISC 360 if the client asks), the load codes (IS 875 for dead, live and wind, IS 1893 for earthquake), the basic wind speed and terrain assumed, collateral and live loads on the roof, and the deflection limits for rafters and columns.

This short paragraph is the most important part of the quotation. It decides the tonnage more than any other choice, and it is the first thing a careful client or consultant will check. It also protects you later if the client changes the brief. Our guide on [IS 800 vs AISC 360 for PEB](https://ganithva.com/guides/is-800-vs-aisc-360-peb) explains how the choice of code affects member design.

## Step 3: Run a preliminary design

Tonnage guessed from past jobs is fine for a first sanity check, but it should not be the number you quote. A preliminary design is quick to set up for a typical PEB:

- Build a frame model for the main portal with the actual span, height, slope and bay spacing.

- Apply the loads from the design basis, including cranes and mezzanine reactions.

- Size tapered columns and rafters for strength and deflection.

- Pick purlin and girt sections and spacing for the governing roof and wall loads.

- Check the end wall frames, bracing and any special frames (crane bays, mezzanine bays, openings).

The goal is not a final design. The goal is a design that is close enough that the final tonnage will not move far from the quoted tonnage. Good design software helps a lot here, because one engineer can try two or three frame spacings in the time it once took to do one.

## Step 4: Build the tonnage and BOQ

From the preliminary design, take off quantities by item group. A clean BOQ for a PEB quotation usually separates:

- **Primary steel:** built-up columns, rafters, end wall columns, crane beams, mezzanine beams.

- **Secondary steel:** cold-formed purlins, girts, eave struts, sag rods, flange braces.

- **Bracing:** rod or angle bracing in roof and walls, portal bracing where used.

- **Sheeting and accessories:** roof and wall sheets, ridge, flashings, gutters, downtakes, skylights, ventilators.

- **Bolts and fasteners:** connection bolts, anchor bolts, self-drilling screws.

- **Extras:** canopies, mezzanine deck, staircases, handrails, doors, louvres.

Keep weights for steel and areas or running metres for sheeting and trims. Our guide on [PEB tonnage estimation and steel take-off](https://ganithva.com/guides/peb-steel-take-off-tonnage-estimation) covers the take-off method in more detail, including the allowances for connections and wastage.

## Step 5: Structure the price

The price structure should be easy for the client to read and easy for your own team to audit. A common structure in India:

- Primary and secondary steel, priced per unit weight, with separate rates where material or process differs (built-up plate sections, cold-formed sections, hot-rolled items).

- Sheeting and accessories, priced per unit area or per item.

- Erection, priced as a lump sum or per unit weight.

- Freight to site, either included or quoted separately.

- Taxes shown separately.

State clearly what is excluded: civil works, foundations, anchor bolt fixing, unloading, cranes for erection, power and water at site. Exclusions that are not written down tend to become disputes.

## Step 6: Review and send

Before the quotation goes out, a second person should spend a few minutes on a fixed review:

- Does the geometry match the enquiry?

- Is the design basis written, and does it match the site?

- Is the tonnage in a sensible range for this span, height and wind zone?

- Are cranes, mezzanines and solar loads included if asked?

- Are the exclusions and validity period stated?

Then send the quotation with a short cover note listing the key assumptions. Clients read the cover note far more often than the full offer.

## Common mistakes that slow quotations or lose money

**Quoting from a rate per square metre alone.** It feels fast, but a taller building, a higher wind zone or a crane can change the tonnage substantially. The loss shows up after the order, when detailed design starts.

**Not writing the design basis.** Without it, the client compares your offer with a supplier who assumed lighter loads, and you look expensive.

**Ignoring end walls and openings.** Large doors and open end walls need extra framing and bracing that a single portal model will not show.

**Leaving secondary steel as a percentage.** Purlins, girts and bracing are a real share of the steel. Take them off from the actual layout.

**Starting from scratch every time.** Most enquiries look like earlier jobs. A library of past designs, standard details and a fixed BOQ template makes every quotation faster.

## Where software fits

The slow parts of quoting are setting up the model, sizing tapered members and taking off quantities. Ganithva does these with its own analysis and design-check engine and exports the steel take-off to Excel, and its dedicated enquiry and quotation support is in development. Whatever tools you use, the estimator and the engineer still own the assumptions, and the engineer approves the design that goes behind the number.

For the next step after the order, see [how to reduce PEB steel cost](https://ganithva.com/blog/how-to-reduce-peb-steel-cost), because the same levers that win the quote also protect the margin.

## Frequently asked questions

### How long should a PEB quotation take?

It depends on the size and complexity of the building and on how complete the enquiry is. A simple warehouse with a full enquiry can be quoted much faster than a building with cranes, mezzanines and unclear loads. The biggest delays usually come from missing information, not from the design itself.

### Should a PEB quotation be based on a rate per square metre?

A rate per square metre is useful as a sanity check, but the quotation itself should come from a preliminary design and a tonnage estimate. Two buildings with the same floor area can need very different steel weights because of span, height, wind zone and crane loads.

### What should a PEB quotation include?

A clear scope, the design basis (codes, loads and deflection limits), building dimensions, a summary BOQ by item group, the price structure, exclusions, delivery and erection terms, payment terms and the validity period of the offer.

### Why do two PEB quotations for the same building differ so much?

Usually because the design basis is different. One supplier may assume a lower wind speed, a different deflection limit or a lighter collateral load. Always compare quotations on the same design basis before comparing prices.